Over GHc3 million Duase warehousing projects defective

A four-warehouse project, rehabilitated at the cost of a little over GH₵3 million at Duase in the Manhyia North district of the Ashanti Region and just handed over to the state, has been classified as having several defects less than five months after completion.

The project, which was awarded to Messrs Seliwas Company Limited, in 2017, to be completed in five months, was originally estimated at a little over GH₵1 million but was revised to a little over GH₵3 million, being GH₵2 million difference.

The expected date for the completion of the project was also revised from April 4, 2018, to May 4, 2018, however, according to officials at the facility the project was handed over in February 2019.

This notwithstanding, parts of the newly rehabilitated facility, handed over to the Ministry of Food and Agriculture (MoFA) for use, has already started showing signs of wear and tear. Three of the four structures – including an office used by the Ghana Commodity Exchange for monitoring – leak heavily when it rains, while other parts have visible signs of cracks.


July 12, 2019